BY: Karen Craigo, Reporter

General contractor: Snyder Construction Group LLC
Size: 30,800 square feet
Cost: $8.6 million
Estimated completion: Early 2026
Project description: An April 2024 voter-approved bond is funding two projects in the Clever School District: renovations and additions to both the high school and elemiddle school, a facility serving elementary and middle school students. The high school is getting a 7,800-square-foot single-story classroom addition and 4,000-square-foot weight room, plus renovations to existing classrooms. The elemiddle school is getting a 19,000-square-foot addition with classrooms, band and music rooms, a weight room and support spaces, with renovations including new secure vestibules and classroom additions and updates. The architect is Buxton Kubik Dodd Design Collective, which is also serving as mechanical, electrical and plumbing engineer, and other engineers are Own Inc., civil; and Coleman Engineering, structural.

Comment